Note: to ensure advanced features like reporting and data quality checks in REDCap work properly, always assign the first form to the first event (order your instruments appropriately). You can link and un-link events in your project during your project set-up and test. Once the project is in production, linking and un-linking events must be done by a REDCap Administrator, because you may lose data if you un-link an event. |
...
Advanced longitudinal set-up (
...
Scheduling can be turned on or off as desired in production or development. Scheduling produces automatically generated schedules by participant based on Arms and Events. The calendar event status can flag “no show” or “cancel” for visit status.
...
optional
...
)
...
On the left navigation bar, select “Scheduling”
Select a record (or create new), define start date (and Arm if applicable), and click “Generate Schedule”
...
Input times and switch scheduled days of the week by changing dates as desired, then click “Create Schedule”
...
You will see a notice that your calendar was successfully created.
...
To see the Calendar, navigate to left Navigation pane and select Calendar under Applications
...
Example: Here you see the time and events for Participant 3
...
From the calendar, you can click on the event and view:
Data entry forms for the participant
Study ID, event, status
Add notes as desired
...