Click on the magnifying glass to the right. Starting typing a topic you wish to learn about

Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

Version 1 Next »

Important Considerations

Upon project creation, all REDCap projects only have a single arm by default. Typically, only a single arm is needed for most project workflows. Arms can be used in the event that a study has groups of different participants, which follow unique workflows, however we discourage using Arms for this use-case and instead suggest the use of (FORM DISPLAY LOGIC).

  • Exporting & Reporting metrics function differently when working with multiple Arms:

    • x, y, z

  • When adding new records to the project, it’s critical the participant be added to the correct arm. Often users forget they have multiple arms causing error.

    • Once a participant is added under a specific arm, there is no built-in REDCap functionality to move the participant to different arm

So when should you use Arms?


The Process

  1. To use ‘Arms’ your project must first be enabled as a longitudinal project

    1. If you project isn’t already longitudinal, this typically indicates you do not/should not utilize the arms functionality! More info: https://utahctsi.atlassian.net/servicedesk/customer/portal/3/article/2341765121?src=1897803665

  2. Navigate to your ‘Project Setup’ page and click ‘Define My Events’

  3. Here you will see the option to add an addition arm

    1. Title Arm & Save

  4. Designate instrument to Arm events (just like you would in a single armed, longitudinal project)

    1. Designate & Save

Additional Considerations